For have a better and deeper cooperation with Thailand customers, VTRONIC planned to get the TISI certificate. The purpose of the audit is to evaluate manufacturing process of the factory to ensure that

1. Product quality complies with the specified standards,

2. The factory has an adequate product quality control system for maintaining consistent product quality incompliance with the standard.

TISI LOGO

 

At 8:40am on December 16, 2019 , we picked up the inspector from the hotel to factory.

At 9:00am, the inspector started hold the meeting to verfiy the scope of the assessment and explained the method of auditing and reporting.

Check documents and records related to the following process:

9:30-10:30 Purchasing: supplier selction&evaluation, raw material specifications, receiving inspection and management of rejected raw materials.

10:30-12:00 Production: the latest records of production process control, product identification & traceability.

12:00-13:00 Lunch time

13:00-14:00 QA: the latest records of final inspection and released products and other product quality testing.

14:00-14:45 Management of nonconforming products, customer complaints, corrective actions and product recall.

 

 

14:45-15:30 Calibration plan and status of measuring, inspection and testing equipments.

15:30-16:30 Walkthrough survey inside the factory to check.

1. Control of raw materials(receiving inspection)

2. Control during production(process control & in-process inspection)

 

Motor workshop inspection

 

3. Control of finished products(final inspection)

4. Control of nonconforming products

5. Suitabilities of machines & equipment used for product and QC

6. Inhous testing laboratory

7. Warehouse and distribution areas of raw materials, work in process and finished goods

16:30-17:30 Prepare for closing meeting

Closing meeting for report the outcome of the assessment. The same personnel who were present at the opening meeting.

 

Wall mounted HRV

 

This auditing factory mainly aim to VTRONIC products, wall mounted HRV, fresh air ventilator. We made full prepartion for the audit factory. All the process are smoothly. Thanks for VTRONIC team and inspector. The certificate is coming soon.